PANAJI
The Joint Electricity Regulatory Commission (JERC) has sought a detailed progress report from the Goa government on the installation of smart electricity meters in the State, including the actual expenditure incurred and cost savings achieved, as the State seeks approval for operational expenditure towards the project.
The Commission has sought details of the progress made during the first year of implementation (2025-26) and the second year (2026-27) up to September 2026, in comparison with the proposed targets. It has also asked the department to specify the actual amount paid to the Advanced Metering Infrastructure (AMI) service provider against smart meters installed and commissioned.
Further, JERC has sought details of the direct cost savings attributable to the AMI project, which could be adjusted against the estimated operation and maintenance (O&M) expenditure for the five-year period from FY 2025-26 to FY 2029-30. The Commission has granted the petitioner two weeks to submit its replies to the queries.
The queries were raised during proceedings on the State Electricity Department's petition seeking approval of operational expenditure for the Advanced Metering Infrastructure (AMI) service provider for smart prepaid metering in Goa under the Design, Build, Finance, Own, Operate and Transfer (DBFOOT) model.
The scrutiny assumes significance as the smart meter rollout in Goa has faced public opposition and was put on hold following concerns over inflated electricity bills. Chief Minister Pramod Sawant had ordered a pause on the broader rollout in June 2026 amid protests by consumers and MLAs, particularly over sharp increases in bills attributed to sanctioned load issues. As of date, the government maintained that smart meter installation in domestic connections remained on hold.
The project envisages covering approximately 6.8 to 7.5 lakh electricity connections across Goa, with an investment of around Rs 890 crore. The implementation has been entrusted to Digismart Networks Pvt Ltd under the Centre's Revamped Distribution Sector Scheme (RDSS) with smart meters being installed to over 1.5 lakh consumers so far.
Goa had initially set March 2023 as the target for smart meter installation under the scheme, which was subsequently extended to March 2024. However, the rollout could not meet the revised deadline and was taken up later.