Oppn puts govt on mat over delay in completion of sewerage projects


.
THE GOAN NETWORK
MAPUSA: The Opposition Congress on Tuesday cornered the government over the delay in completing the sewerage projects in different parts of the State.
Ponda MLA Ravi Naik fired the first salvo referring to the CAG report which indicated that government had suffered a loss of Rs 90 crore for the delay in commencing sewerage projects in the State.
PWD Minister Deepak Pauskar was all at sea when the Ponda MLA questioned whether there were deficiencies in the tendering and execution of sewage projects by Sewage and Infrastructural Development Corporation Ltd.
Pauskar informed that locals objected to the setting up of the sewerage treatment plant at the first site and therefore government was planning to shift the STP to a new site. He further said the government was in the process of identifying the new site.
Contesting the PWD minister’s contention, MGP MLA Sudhin Dhavalikar said the STP matter was challenged in NGT and the green court had given an order in favour of the government. He said the government can go ahead and set up the STP at the same location.
Amidst a barrage of questions, Chief Minister Pramod Sawant assured the House to complete the entire sewerage project in Ponda by 2020.
“All works concerning the sewer lines, household connections and setting up of STP in Ponda will be completed by April 2020,” Sawant said.
Questioning the slow pace of work on the sewerage line in his constituency, Porvorim MLA Rohan Khaunte said he had suggested three sites for setting up of the STP after MLAs of Mapusa and Aldona objected in putting up the plant at Camarcazana in Mapusa.
“We managed to work at micro level on the project and suggested three sites for the STP. But the government is yet to take a call on the site,” Khaunte said.
The chief minister said as soon as a decision was taken on the site, the STP would be set up within one and half year.
Navelim MLA Luizinho Faleiro said work to lay the sewer lines in his constituency has been dragging for more than three years.
“There are three departments “ JICA, Sewerage Corporation and PWD “ involved in executing the sewerage works. There is no coordination among these departments. No one seems to be in the know on what is actually happening,” Faleiro said.
The PWD Minister assured the Navelim MLA to have a site inspection in his area to resolve the issue.
Leader of Opposition Digambar Kamat said most of the sewerage work in the commercial city of Margao was nearly complete except for one manhole.
“Since the manhole is blocked people from that area cannot take house connections,” Kamat said.
The CM assured the Margao MLA to look into the matter and complete the work on the manhole within one month’s time.

SHARE ON

Govt slammed for pvt forest notification

Private Forest Management Policy advocated which gives govt power to decide

The Goan Network
Published Jul 31, 2019, 4:03 AM IST
SHARE ON

the goan I networkPANAJISeveral legislators on Tuesday slammed the government for notifying peoples’ private property as “private forests”, thus making them lose rights over their land. The legislators were speaking during the afternoon session of the Monsoon Legislative Assembly, when demands for forest and other grants were being heard.   Independent Porvorim MLA and former Minister Rohan Khaunte questioned why when Goa had well above the national average of…

READ MORE

Keep Reading — More from GOA NEWS

2 more related stories queued · tap to continue reading

Home HOME News GOA NEWS Global GLOBAL GOENKAR Search SEARCH