Poll code may dump Bainguinim waste plant into next govt’s lap

MAPUSA

The much-delayed Rs 146-crore solid waste management plant at Bainguinim is unlikely to see construction begin before the February 2027 Assembly elections, with the Goa Waste Management Corporation (GWMC) indicating that the process of appointing a project management consultant and subsequently selecting the concessionaire will take another three to four months.

With the election model code of conduct expected to come into force early next year, the corporation is now looking at taking the project forward only after the elections and the formation of a new government.

GWMC Managing Director Harish Adconkar said three companies have submitted proposals for appointment as the project management consultant (PMC), and their technical bids are currently being scrutinised.

A consultant is expected to be finalised after the technical evaluation and subsequent assessment of financial bids.

Adconkar said that once the consultant is appointed, the corporation will proceed with the selection of the concessionaire from among the four companies already shortlisted for executing the project.

The consultant will help finalise the treatment technology, plant layout and other technical aspects before the request for proposal (RFP) is floated for selecting the contractor. "The entire process will take at least three to four months. Work on constructing the plant will start only after the elections, as we may not be able to float the tender during the model code of conduct," Adconkar said. A senior GWMC official said the corporation is attempting to complete the scrutiny of the technical bids by next week. The shortlisted consultancy firms will also have to make presentations before the evaluation process is completed.

The corporation is hopeful of appointing the consultant by the second week of December.

The four companies shortlisted earlier for the project are Hindustan Waste Treatment Pvt Ltd, Srinivas Waste Management Services Pvt Ltd, Organic Recycling Systems Pvt Ltd and HNB Engineers Pvt Ltd. They were shortlisted from six applicants during the initial qualification process.

The proposed 100-tonne-per-day facility is to be developed on a design, build, finance, operate and transfer (DBFOT) basis.

The PMC's responsibilities will include preparation of the detailed project report and feasibility assessment, engineering design, preparation of the concessionaire tender documents and assistance in selecting the agency. It will also supervise construction and monitor the facility through commissioning and performance trials.

The latest development marks another extension in the timeline of the Bainguinim project, which has been awaiting implementation despite the initial shortlisting of private concessionaires.


SHARE ON

Tailor waiting for bus crushed to death under bus chassis in Valpoi

Safety concerns come to fore over chassis transportation

The Goan Network
Published Nov 24, 2026, 11:47 PM IST
SHARE ON
Tailor waiting for bus crushed to death under bus chassis in Valpoi

VALPOIA man from of Valpoi was crushed to death under a bus chassis in Valpoi on Tuesday, highlighting the dangers during the transportation of bus chassis from other states to a bus body building project at Bhuipal-Valpoi.Devanand Surendra Savarkar was waiting for a bus, when a bus chassis which was travelling to the company at Bhuipal struck him at the curve. With the impact, he fell onto the road and got crushed under the rear wheels of the chassis. He was rushed to the…

READ MORE

Keep Reading — More from GOA NEWS

1 more related stories queued · tap to continue reading

Home HOME News GOA NEWS Global GLOBAL GOENKAR Search SEARCH