PANAJI
The long-pending smart road project along Rua de Ourem has finally been revived, marking the last major road development initiative under Panaji’s Smart City mission.
The Rs 38.2-crore project has been tendered, with bidding closing on Friday, November 27. A senior Imagine Panaji Smart City Development Ltd (IPSCDL) official said bids would be opened and evaluated within a week, after which the proposal would require clearance from the Goa State Works Board (GSWB), chaired by Chief Secretary Dr V Candavelou, before work orders are issued.
The 1.4-km stretch runs along the Ourem creek, connecting the old Patto bridge to the Four Pillars junction. It is the only major Smart City road project in Panaji still unfinished, among works involving nearly Rs 1,600 crore in expenditure.
The corridor is a crucial traffic link between the capital and St Cruz. Its redevelopment will include road resurfacing, a new stormwater drainage network, modern street lighting, underground ducts for power cables, water pipelines and optical fibre networks, and extensive streetscape improvements.
The contractor will have 12 months from appointment to complete the work and must ensure traffic movement through suitable diversions and alternative routes during construction, the official said.
Traffic disruption
Execution is expected to be challenging as the road carries traffic from the congested Mala-Fontainhas area towards Bhatlem, Taleigao and Santa Cruz. Residents and commuters could face disruptions throughout the year-long construction period.
Mangrove protection
The creekside location has also raised environmental concerns. However, IPSCDL has assured that no existing mangroves will be affected.