MARGAO
Finally, the upgraded sewer line, fully maintained sewer network, and sump tank have been made operational and have since been functioning effectively in the Matanhy Saldanha Administrative Complex in the South District Collectorate.
Aimed at enhancing sanitation and sewage management at the administrative complex, the infrastructure project was executed by the Sewerage & Infrastructure Development Corporation of Goa Limited (SIDCGL).
This project involved the relaying of the existing sewer line and carrying out comprehensive maintenance of the sewer network, along with the sump tank servicing the premises.
The contract for the said work was awarded to Agasti Enterprises, a registered contractor with SIDCGL, following due administrative procedure.
The formal Work Order No. 387/SIDCGL/Accts.F.10/1759/24-25, dated March 20 2025, was issued to the contractor, stipulating a deadline of 60 days from the date of award for the successful completion of the work.
Although the official work order was issued on March 20, the contractor had already mobilised resources and commenced the work on February 11, demonstrating commitment and initiative to expedite the process.
Sources said the work was diligently carried out and was successfully completed by April 7, ahead of the scheduled timeline.