Arguably, city residents were exposed to contaminated groundwater with leakage of the ageing sewer lines. But while the overhaul of old pipelines is undertaken under the Smart City mission, the dug-up roads, covering over 50 per cent of the city limits, have, in the current scenario, turned into a nightmare for the commoners.
Sewerage work has been taken up first for setting up carefully-designed drainage and sanitation. However, excavated roads have led to chaotic traffic, parking hassles and dust pollution. For motorists who have to be watchful, pedestrians too have to be wary as there are chances of them falling or getting injured due to the uncovered trenches.
The long-term plan that commenced simultaneously with other Smart City projects was slated for execution around three years ago during the stint of Swayandipta Pal Chaudhari, former Chief Executive Officer (CEO) and Managing Director of Imagine Panaji Smart City Development Limited.
The Goan has learnt from credible sources that files were allegedly put in cold storage from 2019 until IAS officers Hemant Kumar and Ravi Dhawan took the charge as the CEOs in their respective terms.
“We realized that the utilization funds will revert to the Ministry of Housing and Urban Affairs if works are not undertaken. With limited time at our disposal, we set things moving and subsequently released plans in January 2022,” an official said.
Poor drainage while carrying out works on 18 June Road had exposed the dire state of the sewerage system. “Waterlogging is an annual problem here. During the cleaning process in 2019, we learnt that the groundwater was getting contaminated due to sewer leaks,” the official said, adding that nearly 80 per cent of old pipelines in the capital which measured 210-300 mm were made of stoneware.
Around 10 of the total 15 zones across Panaji have been undertaken for the sewerage project, which the IPSCDL claims will be completed by April 2023.
“We are replacing the pipelines with High-Density PE which measures 600 mm. It will handle the large-scale transfer of liquids and can withstand high amounts of pressure, unaffected by rust.”
Inconvenience is still a debate that remains unanswered even as the agencies “ Public Works Department, Goa State Urban Development Agency, Water Resources Department and the IPSCDL, argue that the long-term plan that also consists of well-tarred roads and broad pavements with beautification elements will be a respite for the residents for the next 50 years.
The parent agency has also put the onus on the PWD for tarring the roads mindlessly, which has led to shallow excavations.
“The tarring of roads in the past years has been in many layers. That’s how the length of excavation has increased,” the official explained.
Sewer line in Ribandar soon
Panaji’s outskirt Ribandar “ which had no sewer lines “ will now have a proper drainage and sewerage system. An area covering 9.87 km approx., the new pipelines will have the capacity to handle the waste of a population of up to 20,500, considering the year 2050.