SATURDAY, 28 NOVEMBER 2026

Fresh trouble brews for MMC: Pollution Board wants 5TPD bio-methanation plant shifted

Says plant located in insufficient area; seeks action plan for establishing wet waste treatment plant at Sonsodo, compliance report within 15 days

Fresh trouble brews for MMC: Pollution Board wants 5TPD bio-methanation plant shifted


MARGAO
Fresh trouble is brewing for the Margao Municipal Council in respect of the 5TPD bio-methanation plant set up by the civic body at the SGPDA market and the civic body’s future plan on setting up a waste treatment plant.

Not only has the Goa State Pollution Control Board (GSPCB) called for shifting the bio-methanation plant considering the fact that the plant is located in an insufficient area and in close proximity of the market and commercial shops, the Board has directed the Margao Municipal Council to submit an action plan for establishing wet waste treatment facility of suitable capacity at the Sonsodo solid waste management site premises.

The MMC has been directed to submit a compliance report to the Pollution Control Board within 15 days from the date of receipt of this direction. GSPCB Member Secretary Dr Shamila Monteiro has warned that failure to comply with the directions will compel the Board to initiate stringent legal action against the Margao Municipal chief officer under the provisions of the Water (Prevention and Control of Pollution) Act, 1974, and Air (Prevention and Control of Pollution) Act, 1981, without any further notice.

The latest action by the GSPCB comes following an inspection of the bio-methanation plant carried out by a team of officials recently. GSPCB Member Secretary pointed out that the observations in the report of inspection indicate that inefficient operation of 5TPD bio-methanation plant at SGPDA market, Margao is causing environmental pollution in the vicinity. “The location of the existing plant is in insufficient area and in close proximity of the market and commercial shops. Considering the constraints of the area availability of the shed, there will be odour at every instance of unloading and hence it needs to be shifted,” the Board stated.

The Board has directed the MMC to clear the dry waste around the plant premises and stop domestic wash water discharge at the rear side of the plant and outside the premises and to submit an action plan for establishing wet waste treatment facility of suitable capacity at Sonsodo solid waste management site premises.

GSPCB’s direction to the MMC to submit an action plan for establishing waste treatment facility at Sonsodo assumes significance and comes against the backdrop of the fact that the consent to operate the 5TPD bio-methanation plant is valid only for a period of six months.

Inspection report

The inspection of the bio-methanation plant by Board JEL Sidhant Prabhudesai stated that neither supervisor nor any Margao Municipal Council official were present at the time of inspection

The team observed that the 5TPD bio-methanation plant was not in operation at the time of inspection and the collection tank of the shredded/crushed waste was seen to be empty

It was further observed that the opening for pipe at the rear side of the digested slurry collection bed and the opening for pipe on the boundary wall near the rear side of the digested slurry collection bed were still seen to be unsealed. However, no discharge of digested slurry outside the plant premises was observed at the time of inspection

Observation was further made that the area behind the 5TPD bio-methanation plant was seen to be littered with dry waste, adding that garbage collection bins were also seen lying in the area behind the 5TPD bio-methanation plant

Discharge of domestic wash water at the rear side of the plant outside the plant premises was observed from the labourer’s family residing in the plant premises

GSPCB’s conclusion

The 5TPD bio-methanation plant was not in operation at the time of inspection

The opening for pipe at the rear side of the digested slurry collection bed and the opening for pipe on the boundary wall near the rear side of the digested slurry collection bed were still seen to be unsealed. However, no discharge of digested slurry outside the plant premises was observed at the time of inspection

The area behind the 5TPD bio-methanation plant was seen to be littered with dry waste. The digested slurry collection bed was seen to be empty at the time of inspection

Consent to Operate the 5TPD bio-methanation plant has been issued by the Board to Margao Municipal Council on 29/1/2024 with six months validity from the date of issue of the consent


SHARE ON

Cong, BJP faceoff over ‘loyalty vs royalty’ remark

THE GOAN NETWORK
Published Mar 27, 2024, 1:13 AM IST
SHARE ON

MARGAOThe Congress and the BJP were locked in a war of words over “Loyalty” versus “Royalty” remark over the ruling party’s decision to field industrialist Pallavi Dempo for the South Goa seat in the May 7 Lok Sabha polls.A day after Congress leader and Curtorim ZP member Michelle Rebello made a remark over ‘Loyalty vs Royalty’ after Pallavi was given the ticket for South Goa, the BJP Curtorim block slammed the Congress party for the remark. In fact, BJP ST leader Anthony…