MMC has niether set up a waste treatment plant at Sosnodo nor has utilized the existing waste management shed at the site. On the contrary, waste generated in the commercial capital is being transported to the Cacora waste treatment plant. Captured by : The Goan
MARGAO
Post last week’s fire incident at Sonsodo, the Margao Municipal Chief Officer, Melvyn Vaz, has lodged a complaint with Margao Police seeking a probe to determine whether the fire was caused by mischief or was accidental in nature.
Even as the men-in-uniform have initiated a probe into the fire incident, the Margao civic body and the government may have to grapple with the same old question or two: for how long will the civic body continue to spend lakhs of rupees of taxpayers' money on the transportation of the city’s waste to the Cacora waste treatment plant?
And, is the civic body content with transporting the city’s wet and dry waste to the Cacora waste treatment plant, when the A-class municipality is required to have its own plant at Sonsodo? This is especially pertinent when the MMC has spent crores of rupees on upgrading the waste management infrastructure at the dumping site following High Court orders.
The question assumes significance and arises against the backdrop of the fact that the government had assured the High Court in the Public Interest Litigation filed by the NGO Citizens for Democracy through its Secretary, Roque Mascarenhas, that the High-Powered Coordination Committee (HPCC) would soon meet to decide on setting up a 15TPD bio-methanation plant at Sonsodo.
Come December 5, and it will be five months since the High Court instructed the Margao Municipal Council to file a status report/affidavit on, among other issues, the setting up of a 15TPD bio-methanation plant at Sonsodo. The High Court had made this observation after Advocate General D Pangam referred to the setting up of the bio-methanation plant by stating that the Chief Minister-headed High-Powered Coordination Committee (HPCC) would meet and take a decision on the issue of a waste treatment plant at Sonsodo.
Based on the Advocate General’s submission, the High Court had observed, “We expect the HPCC to address these issues as soon as possible and issue necessary directions to the GWMC and the MMC,” and directed the Margao Municipal Council to file a status report/affidavit on the issue in court by July 5, 2024.
Five months down the line, the Margao Municipal Council remains silent on the issue of setting up the 15TPD waste treatment plant at Sonsodo. Not only has the process of establishing the waste treatment plant not been set in motion, but the Chief Minister-headed High-Powered Coordination Committee has not met since the time the High Court disposed of the PIL in March.
Inquiries by 'The Goan' with senior Margao Municipal officials have elicited the same reply: the civic body had written to the HPCC to convene the meeting but in vain. “The civic body has not only written a letter to the government to convene the HPCC but has sent repeated reminders to call the meeting at the earliest. We have still not received any reply from the government on the HPCC meeting,” informed a civic official.
Says the petitioner in the PIL, Roque Mascarenhas: “The High Court had disposed of the PIL by Citizens for Sonsodo with clear directions to the agencies, including the Margao municipality and the government. As per the High Court order, the MMC was mandated to file a status report/affidavit on Sonsodo by July 5, 2024. It will be five months on December 5 now, but the MMC seems not serious about the waste treatment plant at Sonsodo. We will consult our lawyers to knock on the doors of the High Court again.”
Crores spent on Sonsodo upgrades, but waste still treated at Cacora plant
Upon directions issued by the High Court over the past two years, the Margao Municipal Council had initiated a host of measures to improve the garbage handling infrastructure and logistics at Sonsodo by spending crores of rupees.
Margao's city fathers, the municipal babus, and the powers that be controlling the civic body may have to answer a simple question: why did the High Court direct the civic body to improve the infrastructure at the Sonsodo waste management site, with projects worth crores of rupees? Were the measures not intended to facilitate the civic body in setting up a waste treatment facility of its own to treat the 45 tonnes of daily wet and dry waste generated in the commercial capital?
It is sheer irony that, even though most of the perennial issues plaguing the Sonsodo waste treatment site have been largely resolved, the Margao Municipal Council is spending a whopping Rs 15-odd lakh every month on the transportation of the city's waste to the Cacora waste treatment plant.
According to sources, the amount of money spent on waste transportation from Sonsodo to Cacora has already crossed the Rs one crore figure to date, raising the question of whether the civic body, the government, and the powers that be are content with transporting the city’s waste to Cacora instead of setting up a waste treatment plant at Sonsodo.
Take note, ex-Goa Waste Management Corporation Managing Director Levinson Martins had cautioned the MMC not to be content with transporting the city’s waste to Cacora, warning that any disruption of services at the Cacora waste treatment plant would create havoc in the waste management system in the commercial capital.