Ourem smart road may not make the cut before May 31

PANAJI

Work on the 'smart road' along the Rua de Ourem creek from the Old Patto Bridge to the Four Pillars junction is unlikely to be taken up any time soon.

With the May 31 deadline to complete all work set by the State government and endorsed by the Bombay High Court at Goa just a month away there is not enough time to execute the smart road work there from start to finish, an IPSCDL official said.

All other work on this stretch of road like building sewerage chambers and laying the underground cables is completed but there is not enough time until May 31 to start and finish the 'smart road' project which involves laying a concrete road and laying footpaths on either side, the official said.  

The project may now be deferred to after the monsoon in September-October, he added.

SHARE ON

Smart City chaos continues to trouble Panaji residents

THE GOAN NETWORK
Published Apr 29, 2024, 12:17 AM IST
SHARE ON

PANAJIWoes of residents and commuters in Panaji amid the disruptions caused by the ongoing work on multiple 'smart city' projects continue unabated as some of the damage on patched up roads caused by the torrential rain witnessed on April 20 is yet to be rectified at several locations more than a week later.Continuous traffic logjams are being experienced in the area around the Panaji market, particularly in the area around the main entrance gate of the Corporation of the…

READ MORE

Keep Reading — More from GOA NEWS

2 more related stories queued · tap to continue reading

Home HOME News GOA NEWS Global GLOBAL GOENKAR Search SEARCH