The Comptroller and Auditor General in its report for the financial year 2015-16 has rapped the Public Works Department for awarding works substantially above prevailing reasonable rates and when there was only a single bidder despite the work having being rejected by the Goa State Works Board.

PWD gets CAG rap for spending excess money

the goan I network
PANAJI

Referring to a single case of a tender for the ‘Improvement of water supply scheme in Mormugao constituency phase I' the work was sanctioned for Rs 4.78 crore while the administrative approval was granted to the tune of Rs 5.12 crore. When the tender was opened only a single bid was received from one Sheth and Sura Engineering Pvt Ltd for Rs 6.46 crore.
However, in this instance the bid was 40.94% above the estimated cost while the PWD worked out the justified cost to Rs 5.88 crore by m
odifying the quantity and rates of a few items.
However, the Central Public Works Department (CPWD) manual mandates that tenders above five per cent over the justified cost should not be accepted except in peculiar situation and in special circumstances and in these special cases a variation of only up to 10% is allowed.
The negotiating resulted in the bidder reducing his rate from Rs 6.46 crore to Rs 6.23 crore.
While the Goa State Works Board rejected the tender since there was only one bidder, the government directed the PWD to negotiate with the contractor stating that there was an urgency in completion of the work.
In another instance the CAG has found the PWD for using old and substantially higher supply rates for equipment even after the rates had reduced considerably.
"The work was awarded to the contractor at the cost of Rs 6.23 crore which was 36% above the estimated cost of Rs 4.58 crore. This had resulted in acceptance of the single tender at a higher value even after rejection of the tender by the GSWB," the CAG noted in its

Water supply scheme in Mormugao
Work sanctioned for ` 4.78 cr
Administrative approval granted for ` 5.12 cr
Single bid was received from Sheth and Sura Engineering Pvt Ltd for ` 6.46 cr
Higher supply rates
Work awarded to contractor at cost of ` 6.23 cr
Was 36% above the estimated cost of ` 4.58 cr
Results in acceptance of single tender at a higher value even after rejection of tender by GSWB
Altered
measurements
PWD Division XVIII changed measurements on road work by inserting additional figures in the measurements leading to an extra payment of ` 4.85 lakh
Works carried out in Collem in Sanvordem constituency
Results in gain to contractors on the item of supplying DI pipes

SHARE ON

Curtorim ZP by-election: Cracks in Reginaldo camp over nominations

Congress-backed Moreno files his papers while Dionisio files as an Independent

The Goan Network
Published Aug 8, 2017, 3:03 AM IST
SHARE ON
Curtorim ZP by-election: Cracks in Reginaldo camp over nominations

 the goan I networkMARGAO The ruling Curtorim Congress camp owing allegiance to three-time Reginaldo Lourenco appears split over the candidate for the Curtorim Zilla Panchayat by-poll. While the Congress party has fielded Moreno Rebello on the party banner, supported by the Party three MLAs, Reginaldo, Clafacio Dias (Cuncolim) and Filipe Neri Rodrigues (Velim), Dionisio Sardinha has filed his nomination papers as an Independent. That the Reginaldo camp appears divided…

READ MORE

Keep Reading — More from GOA NEWS

2 more related stories queued · tap to continue reading

Home HOME News GOA NEWS Global GLOBAL GOENKAR Search SEARCH