Quality is RITES baby but only on paper?

The RITES report on the Khandepar Highway had reportedly exposed the substandard work carried out. But officials of both the PWD and the contractor MV Rao have apparently succeeded to keep the findings under wraps

The Goa government’s Public Works Department has a standing contract with RITES Ltd for quality assurance. All works worth more than Rs 50 lakhs are supervised for quality control by the Central government’s company under the aegis of the Indian Railways.   

But is the reputed company’s work in Goa gathering dust in rims and rims of bureaucratic red tape?   

The recent case of one major road work -- Khandepar Highway -- seems to indicate so.   

The RITES report on the Khandepar Highway had reportedly exposed the substandard work carried out. But officials of both the PWD and the contractor MV Rao have apparently succeeded to keep the findings under wraps. The contractor firm claims it has not received any such report and they deal only with the PWD. The latter’s officials meanwhile claim that the issues raised by RITES in its report have been sorted out and addressed during the construction process.   

The ground reality and condition of the road meanwhile tell another story and the issues raised by RITES have inexplicably remained only in the files.   

Another measure that officials of the PWD claim ensures quality of work is the Defect Liability Period which the contractor executing the work has to adhere to.   

It is the time period, which for roads is up to three years from completion during which the contractor is responsible for shoddy work and early destruction of roads and other defects.   

During the DLP, the contractor is responsible for repair or to undertake the entire work again without getting any additional payment. But do they, is the million dollar question.   

SHARE ON

Is it really rain or PWD to blame for Goa’s road pain?

Slammed here, there and everywhere for the pathetic condition of Goa’s road network, the government of Chief Minister Pramod Sawant has come up with an elaborate plan with timelines to set things right. The plan it has presented to the Bombay High Court sets itself deadlines of November and December to complete repairs of hundreds of stretches of broken roads it has mapped. It also set a March-April 2020 deadline for completion of new roads already taken up.But why do roads deteriorate the way they do every monsoon, year after year, for decades on end? Is it the monsoon alone to blame? Or is it the famed legacy of lethargy, indifference and corruption in the Public Works Department? ASHLEY DO ROSARIO attempts to unravel the mystery.

The Goan Network
Published Oct 20, 2019, 2:39 AM IST
SHARE ON

Nothing has dominated the public discourse this monsoon more than the debate over the pathetic condition of the roads across Goa.   Be it the national highways, State highways, Major District Roads (MDRs) or the ones in Goa’s cities, towns or interiors of its villages, it would be a miracle to find a stretch of road that hasn’t been battered and left pot-holed with the monsoon.   The condition of roads is the worst in decades and the officialdom will want…

READ MORE

Keep Reading — More from GOA NEWS

2 more related stories queued · tap to continue reading

Home HOME News GOA NEWS Global GLOBAL GOENKAR Search SEARCH