False hopes: Hazardous waste removal at Cuncolim IDC hits roadblock as govt fails to release funds

Six months after receiving approval for a five-crore grant, GSPCB still awaiting funds to start transporting waste to Pissurlem waste dumping site

False hopes: Hazardous waste removal at Cuncolim IDC hits roadblock as govt fails to release funds
The hazardous waste left behind by the Sunrise Zinc at the Cuncolim Industrial Estate. Captured by : The Goan

MARGAO
It was mid-November 2023. An announcement by the chairman of Goa State Pollution Control Board (GSPCB) Mahesh Patil stated that the Board had received a grant of Rs five crore to transport hazardous waste lying at the Cuncolim Industrial Estate, which triggered jubilation and hopes that the IIDC will be finally rid of the two-decade-old hazardous dump.

Powers that be even rushed to claim credit for having forced the government to bow down to sustained pressure to sanction the Rs five crore grant towards the transportation of the waste to the hazardous landfill site at Pissurlem. GSPCB chairman Patil, on his part, had maintained that the pollution control board would set in motion the process to comply with the codal formalities before shortlisting an agency to execute the work of transporting the hazardous waste from Cuncolim IDC to Pissurlem.

Exactly six months down the line, the ground reality, however, has not changed for the better at the Cuncolim Industrial Estate. Leave alone transporting the hazardous waste to Pissurlem, even the process of inviting tenders to execute the work is yet to take off to date.

Reason: The government’s promised grant is yet to become a reality, leaving the GSPCB with no option but to brace up to carry out the annual ritual of covering the hazardous dump with tarpaulin sheets to prevent contamination of water during the monsoons.

When 'The Goan' sought to ascertain from the GSPCB the status of the work of transportation of the hazardous waste from Cuncolim to Pissurlem, chairman Patil was candid in admitting the work could not commence till date. Reason: Other than receiving the letter sanctioning the grant, the GSPCB is yet to receive the promised funds to execute the work.

“Somehow, the GSPCB did not receive the promised grant from the government. As such, we could not set in motion the process to comply with the codal formalities. The process will kick-start as and when the board receives the promised funds,” he said.

Taking no chances and with monsoons just a fortnight away, the GSPCB chairman pointed out that the board has issued an order to cover the hazardous dump at the Cuncolim IDC on a war footing before the onset of monsoons. The GSPCB has been conducting the annual ritual of covering the dump over the last decade after the hazardous dump came under the lens of the High Court following complaints of contamination of water bodies.

The hazardous waste at the Cuncolim IDC was left behind by Sunrise Zinc around two decades ago, throwing up questions about how come the GSPCB and the Department of Environment had remained silent spectators by allowing the company to run the unit when it had no provision to take care of the hazardous waste.

GSPCB plans to rope in NEERI 
to test waste for pollution levels
Even as suspense continues over the release of the promised grant by the government to the Goa State Pollution Control Board (GSPCB) to transport the hazardous waste from the Cuncolim IDC to the Pissurlem hazardous waste dumping site, the Pollution Board is toying with the idea of roping in the National Environmental Engineering Research Institute (NEERI), Nagpur to conduct testing of the waste to check the nature and extent of hazardous substance in the waste.

GSPCB chairman Mahesh Patil told 'The Goan' that the board has asked for a quotation from NEERI to carry out testing of the hazardous waste left behind by Sunrise Zinc at the Cuncolim IDC.

“Since the work of transporting the hazardous waste from Cuncolim IDC to Pissurlem would cost a bomb, the GSPCB has just decided to find out whether NEERI can conduct testing of the waste to ascertain the nature and extent of its hazardous character since the waste has been lying at the site for two decades. If such a test reveals that the waste is no more hazardous, then the question of transporting the waste to Pissurlem will not arise. In the bargain, the government will save precious funds,” he said.

Incidentally, initial estimates prepared by the GSPCB had revealed that it would cost the government a whopping Rs 13 crore towards the transportation of hazardous waste from Cuncolim to Pissurlem.

SHARE ON

Residents of Sacorda, nearby areas suffer water shortage

The Goan Network
Published May 14, 2024, 12:49 AM IST
SHARE ON
Residents of Sacorda, nearby areas suffer water shortage

PONDAThe water level in the Ragada river, which flows through the Sacorda area of Dharbandora taluka, has gone down. This has caused more water problems because a project that supplies water to the area has been closed.Now, women are going to wells in different villages to get water because the piped water supply has stopped. On Monday morning, the panchayat board went to the PWD office and gave a letter to PWD Assistant Engineer Devidas Borkar, asking for more water…

READ MORE

Keep Reading — More from GOA NEWS

2 more related stories queued · tap to continue reading

Home HOME News GOA NEWS Global GLOBAL GOENKAR Search SEARCH